Project Status

CURRENT STATUS OF EBBA SOLAR PROJECT

  • The Ebba Solar team is currently working with Lincoln County on road agreements and project design following the granting of the Special Use Permits for the project in November 2024.
  • Construction is expected to start Q3 2027 with completion and operations in Q3 2029.
  • The project will interconnect to the existing Lincoln Substation, adjacent to Tri-State’s gas plant.
  • The construction haul-route to deliver supplies to the site will be designed to prioritize safety and minimize impact to traffic on roads. Access to the site will be via State Highway 71.

Project timeline

Project timeline for desktopProject timeline for mobile view

Important dates

2024

2025

Q3 2025: Large Generator Interconnection Agreements signed with Tri-State

2027

Q3 2027: First phase of construction

2029

Q3 2029: COD for full build-out